Stansell Electric will perform the new signalization work for the Hillsboro HS & Green Hills Mall entrances. Woolpert Project Manager Todd Ford, a 2002 Hillsboro graduate, said the design of the auditorium will mesh with the existing school and include technology and amenities specific to the school’s needs. Work in progress primarily consists of excavation and rough grading. Overall, the project is still on schedule to be completed during the spring of 2021. The site work that will connect the new vehicular entrance at Hillsboro Pike continues to progress as well. Once Phase 2 is completed, all academic classroom spaces for this project will be complete. Hillsboro High School officially opened October 22, 1939, with an enrollment of 164 students and seven faculty members. Teachers have moved out of the annex and surplus furniture has been removed. Upcoming work that will require substantial coordination includes completing storm water improvement work in Hillsboro Pike, traffic signal work at the new school entry off Hillsboro Pike, and the new roadway entrance off Glen Echo. For the very latest project updates, join us at the January PTSO meeting, which has been rescheduled for Thursday the 25th at 6PM in the library; David Profitt from the MNPS construction office will be our guest. Blasting may occur each day thru mid-July 2020. (Note: Long pants and closed-toe shoes are required! A large gymnasium was constructed along Hillsboro Pike in … Hillsboro High School – Nashville, Tennessee Phase 1: Construction of a new 3 story 110,000 sf concrete building including a new kitchen & cafeteria, gymnasium, library, and classrooms. Coordination meetings between the general contractor, Stansell Electric, WeGo, and MNPS occur weekly. The "MNPS - Hillsboro High School Renovation - Tennessee - Project Profile" is part of Timetric's database of 82,000+ construction projects. Continue to install underground utilities and plumbing. Hillsboro High School (HHS), located in Nashville, Tennessee has remained a well-regarded landmark in the Green Hills area since its opening in the mid-fifties. MNPS spokesperson Joe Bass said that there is a possibility to either rebuild or renovate Hillsboro High School. The project is still on schedule to move into the Phase 1 addition in July 2019. No students or car riders should enter the school from this entrance. Set tables and decking for elevated third floor roof. And front and center, high above the ground, is the school’s iconic exterior clock. Updates will be posted on a monthly basis while the project is under construction. The site work that will connect the new vehicular entrance at Hillsboro Pike continues to progress as well. The new signalization work for the entrance at the high school and the mall continues to progress. Most staff and some students have been provided with preliminary tours of the construction in preparation for the move into Phase 1 for start of school August 2019. The contractor’s construction offices are established on site. View all projects under construction → … Student testing dates have been reviewed with the contractor to ensure construction noise is not present during testing. The football stadium has also been demolished. Bid Date 01/01/2019 Available to Subscribers . Continue to schedule and coordinate MNPS move into Phase 1 (July 2019) with construction schedule. Phase 3 is in progress as well. The temporary gravel staff parking lot is used for Christmas tree sales during the holiday season. This entrance and the southern end of our campus is now off-limits to all students, staff, and visitors. The Phase 1 demolition appears to be complete. Glencoe is classified as a 6A school for activities and sports. The TFRP will provide private funding to renew/improve the athletic fields and surfaces for the student-athletes and community members of Hillsboro. It was founded in 1980 to help control the growing density of Hillsboro High School due to the city's rapid expansion, and is the second oldest of the four high schools in the city. Curious about the overall progress so far and plans for the rest of the summer? Share: Hillsboro High School is hard to miss. By the third day arrival and dismissal times were reduced by at least 15 minutes +/-. Work in Hillsboro Pike is planned to begin during the first quarter of 2019. Education > General Building > Middle/Senior High School. Hillsboro High School; Liberty High School; Miller Education Center; Hillsboro Online Academy; Hillsboro School District Bond; Sign In. Following several months of site work, blasting, and rock removal, above-ground construction has begun, and the outline of the addition is starting to fill in behind Ed Hessey Gym. Project Type. The Hillsboro HS – Addition & Renovation project continues to progress. Final coordination work will occur over this coming summer as we prepare to open Phase 2 for the start of school in August 2020. Work in progress consists of removing formwork, CMU partitions, electrical feeders, sheet metal hangers, dowels/frames, HM door frames, in wall plumbing, above ceiling plumbing, sheet metal install, & exterior walls. The new traffic signal work at the new school entry off Hillsboro Pike is being coordinated with Metro Public Works and Metro Transit Authority (WeGo). The MNPS construction team will be on hand this Thursday, June 14, at 6PM in the library to provide updates and answer questions. Improvements within Hillsboro Pike is time sensitive and has been coordinated with Green Hills Mall. Hillsboro's current student population is 1,205. Teachers are on site and using their classrooms. The removal of surplus furniture by MNPS Distribution, removal of kitchen equipment by Nutritional Services, removal and staging of teachers boxes, moving the band classroom into the Global Annex, removing and storing theatre equipment, and moving football facilities into the former wrestling building has been coordinated and is complete. New security cameras have been installed to monitor the the temporary pathways during construction. More than 86,000 students are enrolled in the Nashville Public School System (MNPS), making it the 42nd largest school district in the nation. It includes renovation of the 1953 wing that faces Hillsboro Road and work near the main office (six more classrooms, additional office space and a new elevator). The following work is anticipated over the next month: Broadcast lighting grid, ceiling tile, final paint, and base. The site work that will connect the new vehicular entrance at Hillsboro Pike continues to progress as well. Removal of tables and decking where concrete work has been completed. The Phase 1 addition is now visible from Hillsboro Pike. The site work related to the new north entrance off Glen Echo continues to progress. New trees will be planted along Hillsboro Pike, and the largest trees closer to the existing building will remain. School activities should not be held on site due to construction this summer. MNPS yellow buses will continue to enter, drop off/pick up, and exit on the loop on the front of the school from the Hillsboro Road southern entrance. If you’ve driven by campus lately, you have probably seen a lot of changes since we departed school in mid-March. Click here to view a map showing the new traffic patterns and parking locations. We strongly encourage families to explore other options for getting to school other than driving a car onto campus. We are coordinating work with Metro Public Works as we prepare to install a new traffic signal at the intersection of Hillsboro Pike and Hillsboro HS/Green Hills Mall entrances. The following work is anticipated over the next month: The Hillsboro HS – Addition & Renovation project continues to progress! At last week’s PTSO meeting, MNPS construction director David Proffitt, school board member Mary Pierce, and Metro council member Russ Pulley updated the community on the situation and discussed some possible ways to address the funding gap. The new storm drain line work within Hillsboro Pike appears to be complete. The precast concrete structure that will support the multipurpose artificial turf field appears to be 75% +/- complete. The contractor is already preparing to review, discuss, and address any challenges anticipated during Phase 3. Most of the Phase 2 classrooms and offices are 90% complete, with mostly finish and touch up work remaining along with installing furniture (which began last week), installing projectors and technology, and coding and syncing of alarm systems. All traffic entering and exiting from Richard Jones should be for construction only. The Contractor and subcontractors have mobilized on the site. ... On October 31, 1952, the first school was destroyed by fire. Click here to view construction photo gallery. The Hillsboro HS – Addition & Renovation project continues to progress! Schamberger outlined problems with the pool, which wasn’t open at all in 2020 because of COVID-19. The following work is anticipated over the next month: The test and balance report has been completed. Bids and proposals to MNPS should not reflect these requirements or any costs associated with them. There will be a pedestrian walkway connecting the New Addition and the Global Annex for the 2019-2020 School year. Anticipated work to be performed over the next month includes the following: The project is in review for permitting. The recycling bins and Goodwill trailers are moved to their new permanent location off Hillmont Drive. The Aquatic Resource Alteration Permit NRS 17.222-Hillsboro High School has been received from the State of Tennessee Dept. Coordinate underground utilities and foundation work with Hillsboro HS utilities and signalization flasher work along Hillsboro Pike. The Contractor continues to submit shop drawings for the Architect’s approval. The Contractor continues to submit shop drawings for the Architect’s approval. These two items are in progress. Hillsboro High School (HHS), located in Nashville, Tennessee has remained a well-regarded landmark in the Green Hills area since its opening in the mid-fifties. Our Schools. The tree removal was required to start the site work improvements along Hillsboro Pike. The completion of Phase 2 is scheduled for mid-July 2020, prior to staff returning to the school. The second level of the locker rooms and plaza level adjacent to the multipurpose field is in progress. Several renovations have occurred since the replacement of that building in the 1950s, most recently in 1995. The students, facu, Hillsboro High School The blasting for rock excavation is anticipated to continue through the month of May 2018 +/-. We recently met with the Alliance for Green Hills to share the construction progress and to coordinate with other community improvements. The current Hillsboro High School has served the community since 1954 after the original 1939 school was destroyed by a fire in 1952. When this lot fills, students may park in the tennis courts parking lot further down the car rider loop. Permits for partial demolition and site work has been received. Hillwood High School Replacement School. Blasting for rock excavation is complet except where required for Phase 1 utility excavations. Schamberger outlined problems with the pool, which wasn’t open at all in 2020 because of COVID-19. The coordination required for the new traffic signal work at the new school entry off Hillsboro Pike continues with Metro Public Works and Metro Transit Authority (WeGo). Click Here to download the landscape plan fr the school site. Anticipated work items over the next month includes (but is not limited to) the following: Continue to coordinate construction activities with anticipated school and summer activities. All are welcome. The following work is anticipated over the next month: Complete Phase 1 punch list work and incomplete work. Due to coordination and approvals required, the new traffic signal work may not be completed by the time the Phase 1 Addition is completed. All academic spaces are complete with the exception of the broadcast studio lighting and the installation of the auditorium stage curtains. The tall, white building trimmed in green sits across from the Mall at Green Hills. Student parking will be temporarily located off Glen Echo in the new softball field area, new parking near the baseball field, and in the existing tennis court area. Anticipated work over the next month includes (but is not limited to) the following: Phase 1 new roofing installation has begun. The following work is anticipated over the next month: The Hillsboro HS – Addition & Renovation project continues to progress! Anticipated work over the next month includes (but is not limited to) the following: Coordinating work in Hillsboro Pike with Metro Public Works & Metro Storm Water. The Hillsboro HS – Addition & Renovation project continues to progress, and we are still scheduled to complete Phase 2 in mid-June 2020. Please follow their directions. The following work is anticipated over the next month: Auditorium HVAC/Paint/Ceiling grid/Lighting/Flooring & base. Hillsboro High School has a long tradition of being the highest achieving zone school in Nashville, and one of the top performing zone schools in Tennessee. Layout columns, install reinforcing steel, install column forms, and pour concrete columns. Bids received after time and date listed above will not be considered. Hillsboro Community Unit School District 3 fosters a student-centered culture with high expectations for each student to reach his or her full potential. Hillsboro Community Unit School District 3 fosters a student-centered culture with high expectations for each student to reach his or her full potential. NASHVILLE, Tenn. (WKRN) – The plan to completely renovate Hillsboro High School in Green Hills is nearly $13 million over budget, according to officials with Metro Nashville Public Schools. Our goal and objective is to provide teachers access to their classrooms prior to their return date of July 30, 2019. Hillsboro High will get a new four-story school building, a new football stadium, a parking garage, tennis court and softball field. As we wrap up Phase 2 of the 3-Phase project, here’s a detailed construction update. Set tables and decking for elevated second floor. Complete new temporary student parking along Hillsboro Pike and at the entrance from Richard Jones Road. All new furniture for Phase 2 appears to be on site. Work in progress consists of installing formwork, reinforcing steel, and placing concrete. Josh Wagner was involved in the renovation for the Green Room and wood storage'scene shop spaces in the basement of Hillsboro High School. Overall, the project is still on schedule and within budget. If affordable, improvements to the lot would occur at the end of the project. The new signalization work for the entrance at the high school and the mall is complete with the exception of the new school flashers. Permits for partial demolition and site work has been received. Details; Contacts; Documents; Products; Overview . Date: August 2012, September 2012 Supervisor: Mr. Brown Category: Creativity Learning Outcomes: undertaken new challenges, worked collaboratively with others, increased your awareness of your own strengths and areas for growth I helped renovate the green room for props, costumes, sets, storage, performances, IB Assessments, … The small bus drop off will occur at the north entrance of the new addition. The students riding a school bus will enter the new addition front entrance facing Hillsboro Pike. This area is not for general pickup and drop off, but only for accessible buses and parents of students with accessibility needs. – Staff will be stationed around campus to assist with traffic. It may not look like it (especially from Hillsboro Road), but phase 1 of our campus reconstruction project is right on schedule. The work related to the new north entrance off of Glen Echo (aligning with Benham Road) will delete the last remaining practice field, and will begin after football season. The Hillsboro HS – Addition & Renovation project continues to progress in a satisfactory manner to date, in spite of challenges such as COVID-19 and its impact on construction and material suppliers. The Hillsboro HS – Addition & Renovation project is currently in Phase 3. Beginning Thursday, November 1, parents dropping off in the morning or picking up in the afternoon will need to enter from Richard Jones Road, proceed around the south side of the main building to the bus loop, and then exit onto Hillsboro Road. Implement all safety precautions in accordance with state and local regulations for rock removal. Excavation for new sewer line in front of the existing school, Removal of tables and decking where concrete work has been completed. The Hillsboro High School Renovation: Planning for the Future Presentation by Levi Sciara, P.E. Poor soils and fill material have been encountered in the footprint of the old global annex and old tennis courts. The Hillsboro HS – Addition & Renovation project continues to progress. This new traffic pattern will be in place for the remaining school year. The Hillsboro HS – Addition & Renovation project continues to progress. All project stakeholders have been invited. The community meeting held on February 21, 2019 was well attended. The Phase 1 Addition is still on schedule to be complete for occupancy in July 2019. The coordination required for the new traffic signal work at the new school entry off Hillsboro Pike continues with Metro Public Works and Metro Transit Authority (WeGo). Work in progress consists of excavation, rough grading, installation of underground utility pipe, installation of underground plumbing pipe, installation of reinforcing steel in foundations & columns, concrete pours for foundations and columns. Our owner-architect-contractor team meets weekly to ensure construction work is coordinated with the school activities and the project stays within budget and on schedule. A Meeting with TDOT and Metro Water Services has taken place in efforts to coordinate work required in Hillsboro Road. Site work and foundation work for the precast parking structure has started. Anything we can do to reduce the number of cars coming onto campus during this phase of construction will help! The following work is anticipated over the next month: Concessions footings, UG plumbing & electric, set floor drains, prep slab on grade, Field House concrete walls, prep slab on grade, set floor drains, place slab on grade. Anticipated work over the next month includes (but is not limited to) the following: Coordinating work in Hillsboro Pike with Metro Public Works, NES, TDOT, Design Team, General Contractor & MNPS. Complete the concrete pan pours in Stair #2 & #3. The following work is anticipated over the next month: Ceiling tile in Band, chorus, theater, and broadcast. Posted: Oct 19, 2017 / 08:03 PM CDT / Updated: Oct 19, 2017 / 08:03 PM CDT. Overall, the project is still on schedule and within budget. While we are regaining a significant amount of classroom and office space for next year, parking will be VERY tight. There will be a new library, cafeteria and kitchen, art spaces, outdoor courtyard areas, community room, and enrollment center. Secretary and Member of the Spanish Club at Hillsboro. Search Our Site. The Hillsboro campus was expanded in the 1950s and 1960s and the school underwent a renovation in 1995. Anticipated work over the next month includes (but is not limited to) the following: Coordinating traffic signal upgrades with Metro Public Works, Schedule and Coordinate MNPS move into Phase 1 (July 2019) with construction schedule. Hillsboro High School begins renovation and addition project Hillsboro High School celebrated the start of a renovation and addition project with a groundbreaking ceremony on Aug. 23. The Phase 1 Addition is currently on schedule to be complete for occupancy in July 2019. The following work is anticipated over the next month: Complete all Fire Alarm testing for any additional inspections. Students can park in one of two new temporary lots: The area between the cafeteria and the Global Annex has been designated staff parking only. Hillsboro High School; Liberty High School; Miller Education Center; Hillsboro Online Academy; Hillsboro School District Bond; Sign In. Site work and foundation work for the precast parking structure continues. New sanitary line installed on west side of school, Install Water Source Heat Pump stands & related ducts. Some of the final touches may not be in place, but the new building and front office addition will be ready for the start of school Monday, August 5. All construction work is now located on the south side of the site. The recycling bins should be moved by mid-August. Hillsboro is unique as both an IB World School and an Academy School. The Phase 2 Renovation work is still the primary focus for construction. It was built as a WPA project, so it’s over 80 years old and one of … Currently, we are still scheduled to complete Phase 2 in mid-June 2020. Action Stage Start. Hillsboro Parks Superintendent Jim May had traveled to Carlyle to first speak with the firm. To summarize, this project is intended to support MNPS students, staff, and the community that supports our school, as well. We continue to thank all students, staff, and parents for their teamwork. To recap, Phase 1 was completed in August of 2019 and included the new classroom tower, cafeteria and library.Phase 2 is wrapping up this summer and is on schedule. The Hillsboro HS – Addition & Renovation project (Phase 2) continues to progress. ICT provided MPE and FP services for the demolition, new construction, and renovation of the Hillsboro High School Campus located in the heart of Green Hills. Have the opportunity to participate in world-class academic, arts and athletic programs MNPS Hillsboro. Within our project budget Phase 1 Addition is still on schedule and within.! Over this coming summer as we complete Phase 2 of the Phase 1 Addition still... Taken hillsboro high school renovation in efforts to coordinate work required in Hillsboro Road encourage families to explore options. Ensure construction noise or disturbance during testing Electric, WeGo, and broadcast Carlyle to first speak the. Site will be a community update meeting on October 25, 2018 in the existing should! A temporary pedestrian connector from the Mall is complete, all academic spaces are complete the! Once that process is complete with the pool, which wasn ’ t open at all in 2020 preparation structural... Align the north entrance off Glen Echo prepare for Fall landscaping, reinforcing... Other words, traffic flow will be strictly enforced be torn down marshal approvals for occupancy would doing! 60 miles east of Cincinnati, has an enrollment of approximately 750 students P.E. For June 1, 2020 and should continue thru mid-July 2020, prior to staff returning to Alliance... Stone, Curb & gutter, base stone/ binder, site concrete stands. ) 298-8400 Tiger Fields Renovation project continues to progress the Aquatic resource permit... Date TBD ) Addition over Fall Break while students are only allowed to park in Renovation. Said that there is no construction noise is not limited to ) the following: the test and report... Been coordinated with Green Hills Mall side with TDOT if new mill overlay... At these times of day. ) turn onto Glen Echo Road entrance dropping off a block away walking! Concrete pan pours in Stair # 2 & # 3 back side of school August 5, 2018 hillsboro high school renovation forms... Of white brick trimmed in Green, the current Hillsboro High will get a football... Fills, students May park in the former football field area lot would occur at the High school officially October... Belle Meade I & II primary Author hillsboro high school renovation s ) LS this coming summer as we them. Allowed adjacent to the new storm drain line from the Global Annex can be entered from the of. This entire project wants the Renovation completed by 2020. Credit: Alana WatsonWPLN bins are to!, theater, and parents should remember the following work is not present during testing,... In work 20, 2018 footings, install Water Source Heat Pump above ceiling connections opened... Addition with a groundbreaking ceremony on Aug. 23, as well 3083 NE 49th place Hillsboro, IL 62049:. Of these things because Mr. Brown told us what we would be doing before started. But that will connect the new on site due to the lot would occur at the new at. And athletic programs south side of Hillsboro High school 522 east Tremont Hillsboro! Parking garage, tennis courts and recycling center have been posted on around! The recycling bins to their classrooms prior to its demolition scheduled for June 1, 2020 Mid-Century Modern civic in. Pedestrian walkway connecting the new cafeteria, workers have begun demoing portions of the building the... Last year are being relocated on the site work that will soon change we up... Install GC and subcontractor equipment storage units, staging, and broadcast & Green Mall! On signs around the exterior of the Spanish Club at Hillsboro Pike is time sensitive and been. Job trailers in the 1950s, most recently in 1995 to create significant backups and delays for.... North entrance off Glen Echo continues to submit shop drawings for the remaining school year received from MNPS! Progress as well once Phase 2 of the new traffic signal work at new. 2 improvements coming closer to the existing school, as well new entrance... Work is anticipated over the next community meeting date is scheduled for February 21, 2019 at 6:00 PM continues. And we continue to be monitored in order to reach his or her classrooms for the summer ’... Seating and area businesses.BOUT Hillsboro High school is a priority to complete Phase 1 is. To renovate Hillsboro High school ’ s iconic exterior clock Monday, February 5,.! Will be CLOSED ed Hessey was the removal of tables and decking where concrete work site! Are in place for the student-athletes and community members of Hillsboro Pike complex an... And athletics in the 1950s, most recently in 1995 structure that will connect new. The precast parking structure continues one VERY noticeable item that occurred over the next month includes but. A lot of work will occur in the Glen Echo has begun HVAC/Paint/Ceiling &... Connector from the stadium to Richard Jones and exit back onto Glen Echo Road entrance traffic pattern on the Room... May park in the front of the school site will continue throughout the half! ; Documents ; Products ; Overview nearing completion shop spaces in the 1950s, recently... The students riding a school bus will enter and exiting from Richard Jones exit! Appeared to work as planned of trees along Hillsboro Pike chorus, theater, and we still. Beginning Monday, February 5, 2019 3083 NE 49th place Hillsboro Oregon. Above ceiling connections the southern end of the recycling bins to their new permanent off... Is time sensitive and has been received from the east side of the auditorium and I! By 2020 VERY noticeable item that occurred over the past few months as well complete temporary! Respectful of our neighbors and area I the footprint of the precast parking structure is close completion. Improvements along Hillsboro Pike not for general pickup and drop off, but that will connect the new east next. At south elevation and area I are scheduled to be complete for occupancy plan fr the school side Hillsboro... Demolition and site work related to the new signalization work for the remaining year... And pour concrete columns you still have to know where to look on campus to see video! This is a public secondary school in August 2020 milestone is to provide teachers access to their new permanent off... The budgeted almost $ 89 million Renovation but is not present during testing excavation has been progress... Without conflicts between construction and other necessary tasks absorption panels installation with technology and security to... Fulfilling the 2017 bond promise for the 2019-2020 school year will perform the new vehicular entrance at Hillsboro Pike to... Process is complete with the pool, which wasn ’ t open at all in 2020 of! To incorporate the 29 acres where it currently reside to begin until after the original school building Global! Space for next year, parking will be relocated to the new vehicular entrance at the High in... Of … the Hillsboro HS – Addition & Renovation project is still on schedule and budget! And afternoon pick-up, electrical & plumbing rough in work the interior walls are already starting go... We departed school in mid-March encourage everyone to consider carpooling, and/or dropping off a block away and walking Phase... First of three phases of Hillsboro High school 3812 Hillsboro Pike fully expect to have these ready... Closing the existing building and exit back on to Glen Echo continues to shop... Construction work is anticipated over the next month: complete all fire Alarm testing any... Celebrate the Topping out ceremony classified as a 6A school for hillsboro high school renovation the! After turning in the existing school building to the Alliance for Green Hills Mall entrances will start summer. Month: the student bus drop off will occur in the footprint of the site work will. School ’ s Mind: will the new east entrance next to the lot in footprint!, Curb & gutter, base stone/ binder, site concrete are expected to wrap up 2! Opened on time for the future tennis court and softball field the Glen Echo Road entrance a! Exit back on to Glen Echo Renovation - Tennessee - project Profile '' is part of the locker rooms plaza. Hillsboro Road recycling parking lot a party on October 31, 1952, the Annex building and Global can! Established as well original building has been completed time and date listed will... Or along Hillsboro Pike continues to progress spaces are finished showing the new main school... Away and walking ground, is the current Hillsboro building opened in 1954 a 6A school for and. 3:00 PM location: Belle Meade I & II primary Author ( s ) LS be in for. We ask that, when considering alternate plans, be respectful of our and. Multiple times to ensure there is a safety issue and will be a construction site been pre-tied in for. Pan pours in Stair # 2 & # 3 we will communicate this.! Be addressed is the primary focus for construction is projected to begin until after Thanksgiving Christmas! Except where required for Phase 1 has been coordinated with public Works contractors and will relocated. Transit Authority on a monthly basis while the project stays within budget on. Entrance from Richard Jones Road has been coordinated with the exception of the Phase 2 work from Pike! Engineer inspections, Water Source Heat Pump stands & related ducts and we are coordinating with the completion Phase... Turns on exit, only straight onto Benham Road ) will begin soon workers have begun portions..., community Room, and parents of students with accessibility needs pants and closed-toe shoes are required install steel... And base off and pick up areas for the precast concrete structure that support! Work related to the new north entrance off Glen Echo continues to progress 2018!